Go to home page
Go to home page
Workers coat the concrete of the BAF structure
Workers coat the concrete of the BAF structure

Monthly report—June 2004

Meeting limits for ammonia
 

Highlights of the month

  • The BAF system to remove ammonia and the UV disinfection facilities continue to treat and disinfect 100% of the Metro effluent prior to discharge to Onondaga Lake. These operations replace the decommissioned tertiary tanks and chlorine contact disinfection system.
  • The equipment supplier, Krüger, began its 30-day performance test on June 6 for the summer season. Initial feedback shows that the BAF system is not only meeting current effluent compliance levels but is performing to meet the required Phase III effluent ammonia limits 4 years ahead of the 2006 ACJ milestone date.
  • Extensive progress was made this month on the Operations-Chemical Building the continued installation of electrical, plumbing and HVAC work.
  • Demolition continued this month for buildings related to the construction of the new Midland regional treatment facility by successful low bidder, Empire Dismantlement Corporation. Demolition is now completed on four residences and one garage. Demolition of 115 Oxford Street apartments slated for July. Asbestos removal began on 115 Oxford Street on June 30.
  • Notices of intent to award bid for the construction contracts for the Phase II Midland regional treatment facility and conveyances will be sent to successful bidders shortly. General contractor to be Murnane. Electrical contract awarded to Ridley Electric. HVAC and plumbing contracts awarded to Edward Joy.
  • The Onondaga Lake Partnership's third annual Lake Day held Saturday, June 5, was well-attended and highly successful.

Progress of projects under construction

Ammonia removal/phosphorus removal combined project (Metro)

(ACJ completion date for ammonia full-scale—11/3/03—revision requested)
(ACJ completion date for phosphorus removal stage II—4/1/05—on schedule)
The façade of the Operations Building visible from Hiawatha Boulevard
The façade of the Operations Building visible from Hiawatha Boulevard

Summary of structural work on major component facilities

BAF structure (ammonia removal), HRFS facility (phosphorus removal), UV disinfection facility and Secondary Effluent Pumping Station: all structural concrete work is complete. contractor working on punch list items.

Operations-Chemical Building. Structural concrete work is complete. The concrete masonry block work is nearly completed, and additional work continued this month with installation of handrails, elevated grating systems, and stairways.

Summary of mechanical work

BAF facility. The BAF facility continued to accept 100% of the Metro secondary effluent flow. Punch list items only remain. Krüger began its 30-day summer performance test on the facility on June 6. Initial feedback shows the system performing well and meeting Phase II and III effluent ammonia limits. Phase II limits were effective May 1, 2004. Phase III limits will be required in 2006.

HRFS facility. With installation of process equipment and piping continuing this month, the mechanical work at this facility is nearing completion. Work includes installation of the balance of piping for process chemicals, installation of the remaining of the seal water panels, and wiring for the panels.

Secondary Effluent Pump Station. Mechanical work in this structure is substantially complete. County is now operating this facility full time.

UV structure. The County took beneficial occupancy of this equipment in May and is now fully operating this facility.

Operations-Chemical Building. Extensive progress was made again this month on all three floors of the Operations Center. All rough-in electrical work is now complete on the first, second, and third floors. Work is now concentrated on the second floor in the mechanical room installing air handling equipment, heating system, and wiring. Lighting drops have been installed throughout all three floors, and all drain and vent lines from the rook through the first floor are complete and tested. Plumbing work is complete on the second and third floors and 90% completed on the first floor. Fire protection has been installed and tested on the third and second floors and is 70% installed on the first floor. Chemical process lines continue to be installed by Danforth, plant water by Burns Bros., and lighting by Ridley Electric.

Architectural work this month

BAF facility. Architectural work continued this month on this structure with installation of the BAF louvers and architectural alucabond panels. This work is now about 98% complete. The County selected a painting system for the upper north and south concrete wall areas of the BAF this month to match the louvers.
Site clean-up work in preparation for parking areas and roads west of the phosphorus facility
Site clean-up work in preparation for parking areas and roads west of the phosphorus facility

Other structures. Roofing is completed on the HRFS structure. No architectural work on the UV structure this month as the contractor is waiting for delivery of the balance of exterior wall panels. Windows were installed in the perimeter of the Operations Center with 75% completed by the end of the month. Other work in the operations center included installation of sheetrock on the third and second floors, painting on the third floor, tile work in the third floor lobby and bathroom areas, ceiling grids on the third floor, and installation of drywall in the elevator room, electrical room, bathroom, and stairwell 1. Fireproofing is also ongoing in the building.

Other information

The contractor is now performing testing of the storm sewer system piping, catch basins, and manholes.

Excavations for the roads and parking lots continued this month with the areas west of the BAF and east of the UV and Sewer Maintenance Building both 90% complete.

Work on main power substation is complete.

Many meetings continue to be held on various aspects of the construction and punch list items with appropriate contractors, consultants, and County personnel.

This is the largest and most costly single project
in the Amended Consent Judgment program

and will have the greatest positive effect on the water quality of Onondaga Lake
by removing more ammonia and phosphorus
from the Metro effluent discharge.

Brighton Avenue sewer separation project (CSO)

(ACJ project milestone—January 1, 2012—project completed)
Pipe installation and restoration work completed: Under this $2.1 million project, 2864 feet of mainline sewer was installed in the streets along with 1760.5 feet of lateral sewers to eighty-four houses, thirty-nine new copper water service lines in the right-of-way, fifteen new manholes, and twelve new catch basins hoods.

This sewer separation project involved about eight blocks on the City's south side. Work included installation of a new mainline sewer and conversion of existing combined lines to use for stormwater only. Lead water services encountered during sewer construction were replaced in the right-of-way by the County to reduce extent of lead services. With the project completed, two former combined sewer overflows (053 and 054) no longer release combined untreated sewage and stormwater to Onondaga Creek when it rains. The overflows now only release stormwater. All wastewater goes to Metro for treatment.

Projects in design stages

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date—Phase II RTF—5/01/04 & Phase III conveyance—5/01/07 milestone revisions requested)

Demolition continues

Asbestos remediation in preparation for demolition at apartment building on Oxford Street
Asbestos remediation in preparation for demolition at apartment building on Oxford Street

Demolition work continued this month for the Midland project. The following structures were demolished this month: a single-family house at 615 Midland AveNUE and a two-family house at 619 Midland Avenue—both demolished on June 4, a former repair-garage building at 519 Midland on June 30, and asbestos removal and disposal began on June 30 at the former apartment building located at 115 Oxford Street.

To date, five structures have been demolished with one structure (115 Oxford Street) remaining.

Post-bid meeting held for phase II of Midland construction

The County held a post-bid meeting with potential successful bidders on the project on June 10 for the construction of Phase II of the Midland project which involves construction of a regional treatment and storage facility and conveyances to carry stormwater and combined sewage overflows to the facility. Notice of intent to award bid to go out shortly.

Other meetings held and business

Meetings were held this month between County staff, program managers (CDM/C&S) and design engineers (EEA) regarding building demolition contract, construction phase services, and review of bids.

Regarding tenant relocation, the Syracuse Housing Authority and the County have agreed on October 1 as the date of final tenant relocation for the project. Final agreement to be signed soon covering relocation services, schedule, and building maintenance.

Agreement reached with Honeywell regarding disposal of soil from the Midland excavation on the wastebeds. Final memorandum of agreement signed by the County—to be signed by Honeywell.

Additionally, discussions continue between County and City officials on the Midland and Clinton projects.

Tallman-Onondaga sewer separation (CSO)

Notice-to-proceed issued

Niagara Mohawk fills a trench on Parkview Avenue where a new gas line was recently placed
Niagara Mohawk fills a trench on Parkview Avenue where a new gas line was recently placed

The notice-to-proceed letter was issued on June 24 to successful low bidder, C.O. Falter, and the first progress meeting was held on June 30. Progress meetings will now be held every 2 weeks. Mobilization on the site will begin in early July. The project is designed to eliminate CSOs 038 and 040 in the Tallman-Midland area and 046A and 046B near Onondaga Avenue on the City's west side. Contract documents signed by Falter on June 18 and by the County Executive on June 22.

Niagara Mohawk has initiated gas line replacements along Onondaga Avenue and several side streets in the 046 CSO basin area.

A public information session was held on Thursday June 3 at the Southwest Community Center with two members of the public attending. Project information was hand-delivered to area residents and mailed to absentee owners.

The total construction of the project is estimated to cost $4.9 million with 70%-30% reimbursement from the U.S. Army Corps of Engineers. Construction is estimated to take 200 calendar days from the notice to proceed. The project will install new sewers and convert existing combined sewers to stormwater only, thus eliminating the release of combined sewage and stormwater from four overflow points along Onondaga Creek.

Projects in facility planning stage

Clinton conveyances and regional treatment facility (CSO)

(ACJ dates—commence construction of conveyances and RTF—May 1, 2003—milestone revision requested.)

  • Facility plan distribution on hold pending outcome of negotiations with City.
  • Final draft environmental information document and draft environmental impact statement/SEQR forms prepared. Release pending outcome of negotiations with City.
  • County and City officials meeting for discussions on project regarding technologies and sites. No resolution reached to date.

The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams streets to be served by a Clinton area facility located near downtown Syracuse. The Clinton CSO Abatement Facility Plan (March 2002 draft) evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system—7/1/02—not implementable—milestone revision requested)
This month, County staff and design consultants, Brown & Caldwell, worked on the following items:

  • Notification letters sent to affected property owners where archeological work is planned. Letters included illustration of the proposed trench locations and description of work.
  • Hartgen has finalized Phase 1B archeological field investigation on multiple sites. Sites to be laid out and trenching to begin in July. Areas disturbed will be restored following trenching. Representative of the Onondaga Nation will be on the site to oversee archeological work along with representatives of Hartgen.
  • Flow meters installed to monitor flows in certain CSOs to aid in analysis of proposed alternatives for collection and treatment. Further monitoring efforts directed at middle basin to confirm flows and analyze potential for CSO elimination.
  • Progress meeting held June 22. Next meeting scheduled for July 13.

The draft Harbor Brook CSO Abatement Facilities Plan was released in March 2002. The draft plan outlines and evaluates alternative technologies including the in-water system for abating and treating the eighteen CSOs that release to Harbor Brook. This draft plan also identifies potential sites for CSO abatement facilities.

Other activities

New trash skimmer boat continues ’04 season

A new trash skimmer boat operated in the Inner Harbor twice a week during the month of June and will continue on the twice a week schedule through August. The new boat was built by Alpha Boats of Weedsport, NY who was the successful bidder on the new 5-year contract with the County to provide floatables debris collection in the Inner Harbor at the mouth of Onondaga Creek. The vessel is larger than the previous boat used for the operation and was constructed specifically for this use. Efforts continue to be made to coordinate cleaning schedule with events scheduled in the harbor.

Lake Day held

Staff of the Onondaga County Ambient Monitoring Program (right) describes improvements in the lake's
Staff of the Onondaga County Ambient Monitoring Program (right) describes improvements in the lake's

Lake Day, sponsored by the Onondaga Lake Partnership, was held on Saturday, June 5. County representative on the Outreach Committee, Sue Miller, served as Chair of this year's event and was responsible for planning and implementation of the event along with publicity and activities.

The event was held in the area near the new Griffin Visitor's Center. The new location and additional activities and displays were very popular with participants. Partnership members were very pleased with the turnout and the public's response.

Lake Partnership activities continue with County representatives taking part in meetings and discussions of the three committees on a monthly basis plus the Executive Committee as a Senior Partner member of the Partnership.

Completed projects

Major milestones met for CSO interim projects

The year 2002 was important in the Amended Consent Judgment program because ten CSO-related projects met their major milestone completion date of July 1, 2002 (ACJ, Appendix B pages 10-12). Some of these interim projects were completed well ahead of the major milestone dates, and all but two met the major milestone. The Kirkpatrick Street Pump Station and the Harbor Brook In-water System required milestone extensions. New York State is reviewing the County's requests for the extensions.

The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer ’02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
     Project changed. Facility plan drafted and published
Mar 2002
     See note 1.
Kirkpatrick Street pump station upgrade and force main
     Construction delays. Project completed by requested milestone revision date of Nov 1, 2002
Nov 1, 2002
1. Milestone revision requested and under review by State.

Brighton Avenue sewer separation project (CSO)

(ACJ Project milestone—January 1, 2012—Project completed 2003)
Pipe installation and restoration work was completed. Under this $2.1 million project, 2,864 feet of mainline sewer was installed in the streets along with a total of 1,760.5 feet of lateral sewers to eighty-four houses, thirty-nine new copper water service lines in the right-of-way, fifteen new manholes, and twelve new catch basins hoods. The project was completed on time and under budget.

This sewer separation project involved about eight blocks on the City's south side. Work included installation of a new mainline sewer and conversion of existing combined lines to use for stormwater only. The County replaced lead water services encountered during sewer construction to reduce lead services.

With the project completed, two former combined sewer overflows (053 and 054) no longer release combined untreated sewage and stormwater to Onondaga Creek when it rains. The overflows now only release stormwater. All wastewater from these areas goes to Metro for treatment.

Major milestones met for Metro interim projects

Under Appendix A of the ACJ, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date and most well ahead of schedule. The projects are listed below by date completed:
 
Project Completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient monitoring program

Summary of sampling program

  • Routine biweekly tributary sampling conducted on June 29
  • Special Lake weekly sampling was conducted on June 2, 8, 14, 22, and 28 with double lake sampling conducted in the south and north deep on June 22
  • Conducted events four and five of ten for the pelagic larval trawls on June 3 and 17 related to fisheries sampling program
  • Electrofishing to be initiated week of May 23 was postponed due to weather conditions to the week of June 6, not completed due to generator failure. Notification was sent to DEC and ASLF.
  • Conducted event one of two for the gill nets for adult fish on June 16 and 17. A lake sturgeon was captured on June 16 in the gill net set in the south basin. The fish measured 1.3 meters and had a tag on it from the Cornell Biological Field Station on Oneida Lake.
     More about the sturgeon.

Other activities

  • Flow monitoring sensors installed at all stations on joint venture project with USGS and the County to collect flow data on the Lake outlet. Initiated installation of water quality monitoring equipment during June. Parameters of measurements will include temperature, specific conductivity, salinity, dissolved oxygen, turbidity, and chlorophyll.
  • Water quality sampling equipment for tributary data enhancement collection project installed on June 30
  • All five of the weather stations that were funded through the Technology Venture Capital Program are operational.

Contracts

Wire staged before installation in the Operations-Chemical Building
Wire staged before installation in the Operations-Chemical Building

New contracts

Sewer separation (CSOs 038, 040, 046A & B): Contract with C.O. Falter Construction Corp. for construction on CSOs 038, 040, 046A & 046B.
Contract amount: $3,598,681. Executed 6/22/04.

Amendments to existing contracts

Midland Avenue Phase II Conveyances & RTF: Contract with CME Associates, Inc. amended for testing services.
Contract amount: $175,000. Executed 6/21/04.

Contract with Wolf Construction Management amended for property management through the month of June.
Contract amount: $8,012.50. Executed 6/9/04.

Change orders

Full-scale ammonia/phosphorus removal: Contract with Ridley Electric Company amended to include various modifications, including the addition of smoke detectors and fire alarm system, wiring of fire-smoke dampers and lightning protection.
Contract amendment amount: $18,786. Executed 6/1/04.

Contract with Burns Brothers, Inc. amended to include various modifications including interconnections of effluent water lines, BAF Seal the addition of shower basins, and relocation of roof drains and fresh air inlet.
Contract amendment amount: $18,029.59. Executed 6/1/04.

Contract with The Pike Company amended to include various modifications, including revisions to UV structure, clean-up of hydrant break, changes to monorail system, and installing epoxy on certain concrete areas.
Contract amendment amount: $78,824. Executed 6/11/04.

Legislative action

Action items of the County Legislature in June: Resolution establishing a public hearing in connection with development of a project at Metro relative to biosolids handling improvements.

Upcoming for July legislative session: Approving a project related to biosolids handling improvements at an estimated cost of $15.1 million and authorizing $15.1 million serial bonds.

Upcoming for July committee: No items.

Funding

Grants

State Bond Act funds

Payments received this month from State Bond Act funds: Midland Avenue Conveyances & RTF: Request #27 in the amount of $660,157.84 received on 6/25/04 for aggregate total of $5,329,651.37. Total received to date in State Bond Act funds: $56,152,643.

Federal EPA funds

Payments received this month from Federal EPA funds: None to report. Total received to date in Federal EPA funds: $46,464,451.

Federal Army Corps of Engineers funds

Sewer separation: final request in the amount of $398,500 received on 6/25/04. Total received to date from U.S. Army Corps of Engineers funds: $5,888,928.

Loans

The following reimbursement payments were received from EFC during the month of June: None to report. Total reimbursement monies received to date through EFC loans for the funded ACJ projects: $159,069,198 (short term), $19,650,766 (long term).

Photos by Bob Bellandi


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection